Our references


Radici Chimica Deutschland GmbH

Radici Chimica Deutschland GmbH, a chemical company belonging to the Italian Radici Group, produces over 100,000 tonnes of adipic acid per year in the Zeitz Chemical Park. The white powder is the raw material for the production of nylon and other plastics, which, for example, are used in the automotive and clothing industries.

To the customer's website


The customised GETEC energy solution

Modern and efficient energy supply concept for the chemical industry.

The challenge

Because the previous steam supply from the power station Mumsdorf was shut down in the summer of 2013, the management of the chemical company was looking for a viable, ultra-efficient and economical energy supply.

The goal

In the context of the supply concept, the idea was to also destroy the climate-damaging nitrous oxide (N2O) that accumulates on site, thereby lowering the greenhouse gas emission.

Our solution

GETEC opted to install two separate shell boilers. One is fired with particularly economical brown coal dust, whilst the other is fired with natural gas.

Facts and Figures

CO2 savings

approximately 100,000 tons of CO2 equivalents per year

Plant

Combined heat and power station with 2 steam boilers and back pressure steam turbine

Supply

Steam, electricity

Installed capacity

Thermal output: 37.1 MW;
Electrical output: 681 kW

We would never have dared to imagine that the problem with nitrous oxide can be resolved with pulverised lignite firing. […] This helps Radici achieve major savings in emissions trading, close to a million euros each year.


Jens Metzner

Plant manager of Radici Chimica Deutschland GmbH in the chemical and industrial park of Zeitz

Our services rendered for Radici Chimica

Energy service contracting

Customised complete solutions - planning, construction, financing, operation

Learn more

Utilisation of specialty gases

Thermal utilisation of climate-changing special gases - pure environmental protection

Learn more

Steam supply

Safe and reliable steam supply

Learn more

Medical Centre Wahrendorff

The head office of the medical centres is located approx. 20 km east of the state capital Hanover in Sehnde, along with the two locations Ilten and Köthenwald. The medical centres provide outpatient, semi-inpatient and inpatient care in emergency psychiatry, psychosomatic medicine and psychotherapy. The entire medical centre has 310 hospital beds and 253 spaces for semi-inpatient care. Personalised and high-quality professional care is delivered to more than 1,060 residents in the different areas of the care home.


The customised GETEC energy solution

The challenge

Supply of the medical centre with heat for space heating, ventilation, hot water as well as electricity, if necessary, produced with state-of-the art, efficient energy generation systems.

The goal

Development of a sustainable heat and energy supply concept for all areas of the medical centre

Our solution

The various buildings are supplied by means of a total of 32 natural gas-based and/or HEL-based heat generation systems.
GETEC set up among other things two CHP units with an electrical output of 140 kW each in the Juliane Wahrendorff medical centre in Ilten as well as in the care home in Köthenwald.
The heat generated in the CHP units is used to supply the base load (heat); the generated electricity is fed into the medium voltage systems of the medical centres Ilten and Köthenwald. The refurbishment and expansion of the local heating network at the same time created combined heat supply systems, which make it possible to switch off heat generation units, thereby optimising the operational life of the CHP units. In the context of their refurbishment in 2015/2016, all heat generation systems were switched to energy-efficient condensing boiler technology.

Facts and Figures

Plant

32 heat generation systems with a total output of 7.4 MW as well as 2 CHP units.

Supply

Heat generation system: Heat for space heating, ventilation and hot water
CHP unit: Heat and electricity

Our services rendered for the Medical Centre Wahrendorff

Energy service contracting

Customised complete solutions - planning, construction, financing, operation

Learn more

Energy partnership

We not only understand our business, we understand yours as well. Your success is our motivation.

Learn more

Fuel management

Sustainable and balanced fuel mix

Learn more

Town of Turek (Poland)

The municipal works in Turek started operating in 1956 and are covering the entire range of communal services. The limited liability company is wholly owned by the municipality of Turek.


The customised GETEC energy solution

The challenge

Nearly 90,000 MWh of heat per year are needed for the properties in Turek with a population of 28,000 residents.

The goal

Above all, the new energy supply was supposed to be particularly economical, to realise low and stable energy costs for the community in the long term.

Our solution

GETEC presented a tailor-made concept and guarantees the town of Turek an economical, affordable and secure heat supply for a total of 30 years. The plan is to build a new plant on the property that was specifically purchased for this purpose. Starting in 2018, the heating station replaced the Adamów power station as heat supplier to the town of Turek.

Facts and Figures

Plant

2x pulverised lignite/gas fired hot water boilers (bivalent burner design)
1x gas fired hot water boiler

Supply

Hot water

Our services rendered for Turek

Energy service contracting

Customised complete solutions - planning, construction, financing, operation

Learn more

Energy generation systems

Energy supply - efficient and decentralized.

Learn more

Fuel management

Sustainable and balanced fuel mix

Learn more

a-ja Resort Grömitz

a-ja, a subsidiary of DSR Hotel Holding, is a new, up-and-coming, rapidly expanding holiday hotel brand. Its aspiration: Best holidays at the best price – hotel and spa for everyone. The a-ja concept represents a democratisation of luxury in the holiday hotel industry, featuring the components adventure gastronomy, generous spa offerings and the ambience of a suite.


The customised GETEC energy solution

The challenge

Set-up of a new CHP unit on the main floor of the a-ja resort Grömitz and hydraulic connection with the district heating network by way of a hybrid station. The strict requirements regarding the permissible noise emission of the Baltic Sea spa town of Grömitz as well as the hotel proper represented a particular challenge, which was considered early on in the planning of the unit.

The goal

In the context of the further expansion of the a-ja brand, a new a-ja resort was completed in Grömitz in 2015, which was connected to the district heating network. An invitation to tender for the construction of an appropriate CHP unit was additionally launched, among other things, for the purpose of generating electricity in-house. 

Our solution

GETEC built a CHP unit with a capacity of 140 kWel using natural gas as fuel base in the building of the a-ja resort of Grömitz.
All of the thermal energy is fed into the upstream district heating network.

Facts and Figures

Plant

CHP unit (cogeneration), hybridisation of district heating systems

Supply

Heat, electricity

Our services rendered for the a-ja Resort Grömitz

Energy service contracting

Customised complete solutions - planning, construction, financing, operation

Learn more

Energy partnership

We not only understand our business, we understand yours as well. Your success is our motivation.

Learn more

Fuel management

Sustainable and balanced fuel mix

Learn more

We embody partnership –
find your contact.

With more than 70 locations throughout Europe, we are always at your doorstep.
Contact us. We are here for you.

Contact
Sie suchen einen Ansprechpartner in Ihrer Nähe?
Einfach Postleitzahl eingeben
Karte wird geladen...