Our references


Medical Centre Wahrendorff

The head office of the medical centres is located approx. 20 km east of the state capital Hanover in Sehnde, along with the two locations Ilten and Köthenwald. The medical centres provide outpatient, semi-inpatient and inpatient care in emergency psychiatry, psychosomatic medicine and psychotherapy. The entire medical centre has 310 hospital beds and 253 spaces for semi-inpatient care. Personalised and high-quality professional care is delivered to more than 1,060 residents in the different areas of the care home.


The customised GETEC energy solution

The challenge

Supply of the medical centre with heat for space heating, ventilation, hot water as well as electricity, if necessary, produced with state-of-the art, efficient energy generation systems.

The goal

Development of a sustainable heat and energy supply concept for all areas of the medical centre

Our solution

The various buildings are supplied by means of a total of 32 natural gas-based and/or HEL-based heat generation systems.
GETEC set up among other things two CHP units with an electrical output of 140 kW each in the Juliane Wahrendorff medical centre in Ilten as well as in the care home in Köthenwald.
The heat generated in the CHP units is used to supply the base load (heat); the generated electricity is fed into the medium voltage systems of the medical centres Ilten and Köthenwald. The refurbishment and expansion of the local heating network at the same time created combined heat supply systems, which make it possible to switch off heat generation units, thereby optimising the operational life of the CHP units. In the context of their refurbishment in 2015/2016, all heat generation systems were switched to energy-efficient condensing boiler technology.

Facts and Figures

Plant

32 heat generation systems with a total output of 7.4 MW as well as 2 CHP units.

Supply

Heat generation system: Heat for space heating, ventilation and hot water
CHP unit: Heat and electricity

Our services rendered for the Medical Centre Wahrendorff

Energy service contracting

Customised complete solutions - planning, construction, financing, operation

Learn more

Energy partnership

We not only understand our business, we understand yours as well. Your success is our motivation.

Learn more

Fuel management

Sustainable and balanced fuel mix

Learn more

Berlin Exhibition Grounds 

Messe Berlin with its fair grounds comprising nearly 550,000 m2 of floor space, 170,000 m2 of hall space (26 halls) and the International Congress Centre (ICC) Berlin is a crucial economic factor for the German capital and is among the ten top-selling trade fair corporations in the world.


The customised GETEC energy solution

The challenge

The energy costs associated with annual heat requirements of approx. 60 million kWh and power requirements of approx. 37 million kWh as well as the associated CO2 emissions represent a significant locational factor. GETEC was asked to develop a cost-efficient and sustainable solution.

The goal

Therefore, Messe Berlin’s goal was to lower the energy costs and the CO2 emissions.

Our solution

Energy savings performance contracting and innovative plant engineering enabled GETEC to lower the energy consumption of Messe Berlin by approximately 30%. This saves approx. 10,000 tonnes of CO2 emissions per year.

Facts and Figures

CO2 savings

approx. 3,000 to 4,000 tons per year by means of a wood pellet boiler

Plant

Boiler system, pellet boiler unit, CHP unit, cooling system 

Supply

Heat, cold, electricity

Our services rendered for Messe Berlin

Energy service contracting

Customised complete solutions - planning, construction, financing, operation

Learn more

Fuel management

Sustainable and balanced fuel mix

Learn more

Supply solutions

Simple and reliable supply - with GETEC

Learn more

UNESCO world heritage site housing estate "Weiße Stadt" in Berlin-Reinickendorf

The successful transition toward renewable energies is a collaborative effort. GETEC in cooperation with real estate companies has been developing successful energy efficiency initiatives since 2013. The foundation was laid with Deutsche Wohnen SE and the milestone project “Weiße Stadt [White City]” of the joint energy services company G+D Energiemanagement mbH. 


The customised GETEC energy solution

The goal is to generate additional profits with a sustainable and consistent realisation of all possible savings potentials.

The challenge

Supply of approx. 2,500 households with heat / combined heat and power station and district heating network with 31 substations

The goal

Reduction of the primary energy factor of the Weiße Stadt district heating territory from 1.3 to 0.89

Our solution

•  Set-up of 2 x 5.8 MW hot water boilers
•  Maximum energy efficiency by using economisers in the waste gas stream of the hot water boilers
•  Set-up of an ultra-modern CHP unit (1 MWel)
•  Feed-in into the public 10 kV grid

Facts and Figures

CO2 savings

Reduction of the emission by 3,800 t/a

Plant

Ultra-modern CHP unit (1 MWel) with a total thermal capacity of 12,550 KW

Supply

Heat

Our services rendered for Weiße Stadt

Energy service contracting

Customised complete solutions - planning, construction, financing, operation

Learn more

Strategic partnerships

Energy efficiency cooperations between strong partners

Learn more

Ancillary cost optimisation

Full service for industry and real estate

Learn more

Haltermann Carless Deutschland GmbH

Haltermann Carless Deutschland GmbH is one of the leading European manufacturers of speciality chemicals and hydrocarbon-based solvents. The product portfolio comprises printing ink oils, high purity hydrocarbons, hydrocarbon-based blowing agents, and test and reference fuels.

To the customer's website


The customised GETEC energy solution

Modern and efficient energy supply concept for the chemical industry.

The challenge

The existing supply of power to the plant using thermal oil and steam no longer met current demands and efficiency criteria. A new supply concept was to be developed to ensure the future security of supply.

The goal

The vent gas produced on site in the storage tanks should also be utilised as an energy source and thus used efficiently and in an environmentally-friendly fashion instead of being discarded in thermal post-combustion as was previously the case.

Our solution

GETEC developed a highly efficient, sustainable and economical supply concept that supplies the entire production site in Speyer with thermal oil and steam. The GETEC engineers opted to use two thermal oil boilers fired with natural gas and a steam generator indirectly heated with thermal oil. What makes this procedure so special The vent gas that accumulates during the production is thermally utilised in the system.

Facts and Figures

CO2 savings

approx. 2,800 t/a

Components

2 natural gas fired thermal oil boilers
1 indirect steam generator

Supply

Thermal oil with a flow temperature of 340°C
Saturated steam with a pressure of 23 bar (above atmospheric) and a temperature of approx. 222°C

Installed capacity

Nominal heat output of the thermal oil boiler: 8,300 kWth each
Steam output of indirect steam generator: 13 t/h

Our services rendered for Haltermann Carless

Energy service contracting

Customised complete solutions - planning, construction, financing, operation

Learn more

Utilisation of specialty gases

Thermal utilisation of climate-changing special gases - pure environmental protection

Learn more

Decentralised energy supply

The future is decentralised. For more efficiency, more independence and more flexibility.

Learn more

We embody partnership –
find your contact.

With more than 70 locations throughout Europe, we are always at your doorstep.
Contact us. We are here for you.

Contact
Sie suchen einen Ansprechpartner in Ihrer Nähe?
Einfach Postleitzahl eingeben
Karte wird geladen...